Residential Project Planner & Milestones
Track the sequential stages of your home construction, duration schedules, critical quality inspections, and material readiness checkpoints across 34 scheduled weeks.
1. Site Mobilization & Earthwork Excavation
Site Preparation · Duration: 3 WeeksClearing site vegetation, soil leveling, layout demarcation with builder's string, and foundation trench excavation to firm bearing strata.
2. Foundation & Substructure Casting
Substructure · Duration: 4 WeeksPlain Cement Concrete (PCC) bed, footing rebar cage installation, column starter casting, plinth beam tying, and compacted backfilling.
3. RCC Superstructure Framing & Roof Slab
Structural Core · Duration: 7 WeeksReinforced column casting, shuttering staging, beam cage tying, slab steel laying with cover blocks, and monolithic concrete casting.
4. Brickwork, Masonry & AAC Partitions
Enclosure · Duration: 4 WeeksConstructing 9-inch exterior structural perimeter walls and 4.5-inch interior partition dividing walls with lintel bands over openings.
5. Concealed MEP (Electrical & Plumbing)
Services · Duration: 3 WeeksWall chasing, conduit routing, electrical modular backbox embedding, plumbing drainage drops, and concealed water pipeline layout.
6. Internal & External Plastering & Waterproofing
Protection & Finishes · Duration: 5 WeeksApplication of 12mm internal cement plaster, 20mm double-coat external sponge plaster, and polymeric elastomeric waterproofing of wet areas.
7. Flooring, Tiling & Joinery Framing
Surfaces · Duration: 4 WeeksBedding mortar screed, tile adhesive application, floor tile leveling, marble door frames, and door/window shutter fixing.
8. Painting, Sanitary Fixtures & Final Handover
Handover · Duration: 4 WeeksTwo coats of wall putty, primer sealing, 2 coats of premium emulsion, electrical switch fitting, sanitary fixture connection, and deep site cleaning.